Winnipeg Free Press

Bike-path work overkill: official

Bureaucrat concedes workload daunting for city, residents

By: Bartley Kives

The official in charge of Winnipeg's $20.4-million active-transportation upgrade that has sparked criticism and controversy says he hopes the city won't attempt such an ambitious bike-and-pedestrian overhaul in a single year ever again.

In an interview with the Free Press, public works project manager Bill Woroby suggested what Mayor Sam Katz and other senior officials have refused to concede over the past week -- that this year's 36-project upgrade was too ambitious to tackle over the course of one construction season.

"Hopefully not," said Woroby when asked whether Winnipeg should ever repeat this year's attempt to add 102 kilometres of cycling routes to the city's existing 274-kilometre network. All three levels of government paid for the project, the largest commuter-cycling upgrade ever attempted in Winnipeg.

"It's hard to deliver 30-odd projects in one year. Not only are there 30-odd projects, you're undertaking public consultation at the same time and introducing people to new facilities they're not used to," Woroby said.

"This has certainly challenged the delivery. It has not given the public the opportunity to appreciate the facilities we have in place. Once people see the completed project, they will see it as a great addition to the city."

Katz and other officials have repeatedly said the tight time frame for the ambitious slate of projects had nothing to do with a public-consultation process both he and mayoral challenger Judy Wasylycia-Leis have described as a failure.

Federal infrastructure-funding rules require the projects to be finished before the end of March 2011, which effectively means all but three parts of the upgrade must be finished before the winter, when snowfall makes it impossible to lay concrete.

One project, a $1-million bridge in Omand Park, was cancelled and replaced with $100,000 worth of path improvements. A second, the $250,000 Bannatyne-McDermot Bikeway, is in limbo to allow more dialogue with residents and businesses.

A third, the Assiniboine Bikeway, is nearing completion despite a lawsuit six Broadway-Assiniboine businesses have launched. There's also opposition to projects along Berry Street, Grosvenor Avenue, Sherbrook Street and Harrow Street.

As of Tuesday, 32 out of 34 green-lighted projects were either under construction or nearing completion, said Woroby. Construction on the final two will begin shortly.

Woroby dismissed suggestions a round of cuts to the public service last year had any effect on the projects or their public consultation. "We did what was required, with the resources we had in hand," he said.

The city employed seven consulting firms to engineer what were originally 36 projects, while two other firms were hired to co-ordinate the upgrade. The city asked private firms to conduct the public consultations last November, but cancelled the search four days before it closed.

Former city communications manager Ed Shiller said he felt $125,000 was too much to spend on public relations consultants. He said the city did a good job engaging the public on its own early this year, beginning at Katz's state of the city address in January.

"We produced fantastic literature, describing every single one of the projects then under consideration. Then we set up a whole series of public consultations," said Shiller, who left the city at the end of March.

After his departure, private consulting firms took over the communications strategy as well as the public-consultation meetings. Woroby said the city responded to the advice it received at all of the meetings.

But even active-transportation proponents say the public ignored these events.

"I was at 99 per cent of those consultations and the turnout was minimal," said Janice Lukes, executive director of the Winnipeg Trails Association. "No one reads the notices, but when the bulldozers are on the street, then people perk up. It's too bad. I just hope someone has the balls to keep things moving forward."

Others want more projects placed on hold. Ellice Cafe and Theatre manager Belinda Squance, for example, plans to meet with public works director Brad Sacher this week to convince the city to shelve the $228,000 Sherbrook/Maryland bike-lane project until parking issues in the West End are addressed. Squance said she supports cyclists but wishes the city actually studied where they go.

Other cycling advocates complain the upgrade was a rush job.

"A tight timeline for the project and the need to spend federal funds within this timeline no doubt was the issue in regards to actively engaging others," said Downtown BIZ director Stefano Grande. "Active transportation has to be part of the overall infrastructure strategy, not an afterthought (that involves) trying to fit a peg in a hole."

Katz's campaign described the ongoing headaches as "growing pains."

bartley.kives@freepress.mb.ca

Cash for cycling routes

Spending on active-transportation in Winnipeg over the past five years:

2006: $200,000

2007: $1.75 million

2008: $2.65 million

2009: $4.4 million

2010: $20.4 million (allocated)

The 2010 active-transportation plan

On Sept. 11, 2009, all three levels of government pledged to spend a combined $20.4 million on 36 active-transportation projects in Winnipeg. The cash was supposed to add 102 kilometres of cycling and walking routes to an existing 274-kilometre network.

Here's what the project was supposed to build:

New pathways dedicated for cyclists: 28 kilometres, for 15 separate projects.

New separated bike lanes on city streets (the Assiniboine Bikeway): Two kilometres.

New bike lanes on streets with "sharrows" (the Bannatyne-McDermot Bikeway): Eight kilometres.

Other new cycling routes on city streets (18 separate projects): 64 kilometres.

New bike-and-pedestrian bridge (Omand Park Bridge): One.

Here's where the projects stand right now:

Projects completed or nearing completion: Eight.

Projects under construction: 24.

Projects awaiting construction, with tenders awarded: Two.

Projects on hold: One. The city has put the brakes on the $250,000 Bannatyne-McDermot Bikeway.

Cancelled projects: One. Wolseley residents rejected plans for the $1-million Omand Park Bridge. It's been replaced by $100,000 worth of path upgrades in the park.

-- Sources: City of Winnipeg


--
Beth McKechnie
Workplace Commuter Options
Green Action Centre
204.925.3772
www.greenactioncentre.ca
 
Green Action Centre is a registered charity. Please consider making a donation.
 
Coming to the EcoCentre? (3rd floor, 303 Portage at Donald, MEC bldg)

Enter via the elevator just inside MEC's front doors
Bike racks are located in front of MEC