Project Milestones
Task Milestone Date
Project Work Plan February 16, 2020
Background, Existing Conditions, Challenges & Future Options August 31, 2020
Transportation Modelling of Future Options October 30, 2020
White Paper outlining key findings November 30, 2020
Development of Draft TMP Core Framework Study January 29, 2021
Development of Cost Estimates, Benefit / Cost Analysis February 26, 2021
Final TMP Core Framework Report March 31, 2021
Final Transportation Master Plan By others by (June 30, 2021 )