Waverley Underpass
Construction Update #3
Fall is here and the next phase in the construction of the Waverley Underpass will begin shortly.
Construction Work to Date
Preliminary works on the road and rail detour, intersection improvements, and reconstruction of Waverley between Taylor and Grant are nearing completion.
Temporary Weekend Closure
To complete final detour construction work there will be a temporary weekend closure of the project area.
·Closure starts Friday, September 29, 2017 at 5:30pm
·Closure ends Monday, October 2, 2017 at 6:00am
·The project area will be closed to all vehicles, pedestrians, and cyclists, refer to map at right for details
·Property owners will have access via other routes and access points
·Additional communications will occur if closure dates change or the closure dates need to be extended
Detour Restrictions
On Monday, October 2, 2017 immediately following the weekend closure, traffic will begin operating on the Waverley Detour roadway.
A multi-use path for pedestrians and cyclists will be provided along the west side of the detour. The detour will cross the CN Mainline at a temporary at grade crossing.
While traffic is operating on the detour, a number of turning movement restrictions will be in place. Refer to the
Detour Map at right for details. Detour turn restrictions include:
• Eastbound Taylor at Waverley (detour) must turn right
• Northbound Waverley (detour) at Taylor, no left turn
• Southbound Waverley at Taylor, no left turn
Future Construction Work
With traffic on the detour, construction of the Underpass Bridge and roadway will proceed over the following two years. Traffic is expected to transition back under the new underpass
in the Fall of 2019.