On behalf of Project Manager, Alex Sopilnyak please see shutdown request for CERAMICS BUILDING.
Start End Details
|
Date(s): |
Jul.21 |
Aug.14 |
|
|
Times: |
8am |
4pm |
|
|
Scope:
(description of shutdown work with room #’s) |
|
|
On Jul 21st shutdown main power, affecting MUA1, fire alarm & monitoring. GC will hook up to temp power generator and building systems will be restored. Contractors will be demolishing old 300KVA 4160:120/208V transformer and install new 500KVA 4160:120/208V transformer.
Building power will be shutdown again on Aug 14th to remove from temp power and put back on new transformer. |
|
Workorder Required (indicate shop(s): |
|
|
ELEC-FA – to shutdown FA for power switch , CTRL – check everything comes back up after switch |
|
Building Notification
(Yes or No): |
|
|
No, building SPCs have been made aware |
|
Notification: |
|
|
|