On behalf of Project Manager, Alex Sopilnyak please see shutdown request for CERAMICS BUILDING.

 

                                                                     Start                  End           Details

Date(s):

Jul.21

Aug.14

 

Times:

8am

4pm

Scope:

(description of shutdown work with room #’s)

 

 

On Jul 21st shutdown main power, affecting MUA1, fire alarm & monitoring. GC will hook up to temp power generator and building systems will be restored.

Contractors will be demolishing  old 300KVA 4160:120/208V transformer and install new 500KVA 4160:120/208V transformer.

Building power will be shutdown again on Aug 14th to remove from temp power and put back on new transformer.

Workorder Required (indicate shop(s):

 

 

ELEC-FA – to shutdown FA for power switch , CTRL – check everything comes back up after switch

Building Notification

(Yes or No):

 

 

No, building SPCs have been made aware

Notification:

 

 

 

 

Thank you,

 

Traci Friesen, BES