FW: New Window project placement schedule
A reminder of the Window project placement schedule and the room prep that needs to happen prior to the new window install date.
Also, for those approved to work evenings/weekends, it is acceptable to be in the building during the evening/weekend hours as long as you do not enter the room where window work/asbestos abatement is occurring.
The area outside of the construction fence in the West side courtyard/greenspace can be used by the buildings occupants. DO NOT enter the inside of the fenced area of the construction site!
Thank you,
From: Bev Godard Sent: April 27, 2021 8:51 AM To: plants-all@lists.umanitoba.ca Subject: New Window project placement schedule Importance: High
Good morning,
Attached is the new window project placement schedule. Please review and let me know of any issues by Friday April 30th. Also, attached is the room prep example.
General overview of the schedule is:
* Mobilize May 10 * Rm 113 window mock-up week of May 17 * Mock-up window testing tentatively May 26 * Tackle all of the west elevation first and then move to east elevation * Rm 210 work and window - week of August 23 (2 weeks) * Completion October 6
Reminder that all items within the 4 to 5 foot area in front of the exterior window wall in each room should be removed prior to the room's date identified in the schedule. For example all items within the area of the window in room 113 will need to be moved prior to May 17th.
Thanks, Bev
Bev Godard Secretary to the Department Head Department of Plant Science University of Manitoba 204-474-8563 Bev.godard@umanitoba.camailto:Bev.godard@umanitoba.ca
participants (1)
-
Bev Godard