On behalf of Project Manager, Alex Sopilnyak please see shutdown request for CERAMICS BUILDING.
Start End Details Date(s): Jul.21 Aug.14
Times: 8am 4pm Scope: (description of shutdown work with room #'s)
On Jul 21st shutdown main power, affecting MUA1, fire alarm & monitoring. GC will hook up to temp power generator and building systems will be restored. Contractors will be demolishing old 300KVA 4160:120/208V transformer and install new 500KVA 4160:120/208V transformer. Building power will be shutdown again on Aug 14th to remove from temp power and put back on new transformer. Workorder Required (indicate shop(s):
ELEC-FA - to shutdown FA for power switch , CTRL - check everything comes back up after switch Building Notification (Yes or No):
No, building SPCs have been made aware Notification:
Thank you,
Traci Friesen, BES Project Administrator || Architectural & Engineering Services University of Manitoba 118-89 Freedman Cres. C: 431-374-8140 Out of Office: Fridays in July